How to get a report at the portfolio level for resource capacity planning

Ann Bouvier
Contributor
June 12, 2020

For capacity planning, how do I get, at the portfolio level, a list of resources per sprint, what they are working on.

Need this to see if/when we have availability if we were to fast track a new project.

2 answers

1 accepted

0 votes
Answer accepted
Shawn Kessler
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
June 16, 2020
0 votes
Tina Behers
Community Champion
June 17, 2020

Hi @Ann Bouvier 

It's not possible today to get that view in Jira Align.  The closest you can get to that traditional waterfall type view is the Program Allocation Report 

I use the reports landing page to access this: 

 

In Tier one - select the Portfolio and the PI - Then you can use the Program selection within the report to scroll through the Trains.

Screen Shot 2020-06-17 at 8.04.36 AM.png