The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results forĀ 
Search instead forĀ 
Did you mean:Ā 

Anything we should care about when integrating one FishEye with two JIRA instances?

Daisuke Niwa
Contributor
June 17, 2012

Hi there,

I believe it is possible to integrate one FishEye with two JIRA instances via application link.

Is there anything we should care about when we opt for the above configuration? Especially, should we care about performance, any duplication of commit message etc?

Please let us know.

Regards,
Daisuke Niwa

1 answer

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Answer accepted
Daisuke Niwa
Contributor
June 19, 2012

I've asked this question to Atlassian support.

Basically it should work fine so long as you separate project keys between JIRA instances.