The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Task Report Macro - showing multiple lines?

boardtc
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
January 9, 2018

The Task Report Macro just shows the text on the same line as the checkbox, which is very useful.

Often as well as checking a task as done there is a comment added.

The only way I have found to have any additional text included in the task report is to continue writing text on the line (auto-wrapping), if you do a line break the text will not show. The result is typically a poorly formatted comment.

Is there any way to hack showing multiple lines of text for the same task?

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

1 vote
AnnWorley
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
January 10, 2018

Hi Tom,

I tested on Confluence 6.6.1 and the Task Report macro is showing comments made after carriage returns in the task list:

Screen Shot 2018-01-10 at 12.45.34 PM.pngPlease let me know your version of Confluence - it is possible that this was recently fixed although I did not find a bug report for this specific issue. 

I could be misunderstanding your use case, just let me know where I am going astray, if so.

Cheers,

Ann

boardtc
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
January 12, 2018

That helped my troubleshooting!

My issue turned out to be that after my CR for comments I was including bullet points (not checklist items) and that stops the text being included!

A workaround is to use a -- for the bullet :-) But all comments must be indented on the same tab as the tasklist item. Note, bullets can be copied and pasted in the task list item.

outstanding actions.png

boardtc
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
January 12, 2018

Any issue I have found, is that you have to be very careful retro editing pages as described above. If the checkbox changes to a bullet and then you revert to a task list and then recheck the box the Completed Date gets updated.