I would like to produce a task report that only shows the open tasks taht have not been assigned to a team member. These tasks appear in the task report. However I always get all the assigned tasks as well.
My hope was to use the "assigned to" field, but I have no idea how?
Hello Jens,
Task Report macro can't output unassigned tasks only. But you can use Table Filter macro to show unassigned only.
Thanks, Andrey, that works for me
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.