The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Update JIRA issue automatically once pull request is approved.

Vikas Dogra
December 14, 2012

Is there a way to update the JIRA issue automatically once a pull request from stash is approved. I guess i can add a script in hooks directory and call jira-client for update but is there built-in feature in stash which i can use. Are you planning for this feature in future releases?

1 answer

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Answer accepted
cofarrell
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
December 14, 2012

Hi Vikas,

At the moment I'm afraid there isn't anything built-in to Stash. For now you could certainly add a manual hook, although my suggestion would be to write a plugin that listens for the PullRequestMergedEvent and then uses ApplicationLinks to update the relevant JIRA issue.

Regarding future plans, we are certainly thinking long and hard about how best to provide this functionality. I'm afraid I couldn't give you any concrete dates, but you might want to keep an eye on STASHDEV-2754, which is part of the biggest story STASHDEV-2491.

Cheers,

Charles