Hello,
we are using a cron for executing a build three times daily. What we would like however is to have it run at 07:40, 12:00 and 16:00 due to another part of the system being built at 07:00 daily.
We are currently running it at 07:40, 12:40 and 16:40 to avoid the issue.
Is there any simple way to use two cron expressions?
Community moderators have prevented the ability to post new answers.
Yes, by configuring two cron triggers.