Hello, I'm using one of the new scriptrunner canned scripts, called 'Show Parent Issue in Hierarchy'. My goal is to have a field that shows the Initiative that a story relates to. Our Portfolio hie...
On top of the standard notifications JIRA offers, does Portfolio offer any additional notifications? We were wondering if we can have Portfolio users notified in case the underlying content of a plan...
I understand there currently is a limit for loading 5,000 issues into a portfolio plan. Also saw that a corresponding feature request for increasing this limit has already been created (https://jira....
Currently I am working within a JIRA instance that has many projects with many versions (think of a lot of minor versions like "1.0.1", "1.0.2", "1.1.0", "1.1.1" etc). This is resulting in a Portfoli...
So when a project kicks off we know that we dont know all the stories, how does Jira porfolio account for that? we are just about to start using it but I dont know how I will be able to estimate end ...
The latest release of Portfolio for Jira on server doesn't appear to offer quite the same feature set as the cloud version. Is there a feature comparison matrix or document comparing the two of them ...
I have created a plan in JIRA portfolio. Post plan creation, I have added stories and estimates... as well as burned down other stories. I am looking for a way to update this in Portfolio
We are looking to add Themes to our Portfolio plans. Currently when you add Epics to Themes, the dates on the Themes "adjust" based on the dates in the Epics. We would like to know if the following s...
In portofolio under 'scope' one can see the issues that belong to your selected release. On the bottom I see a list with the issues I've added in Jira to this version (in the issue 'fix version' = r...
I must be missing something obvious but I can't see how to add existing Jira Epics to an already created Plan. (When I created the Plan I was getting server timeouts. The only way around ...
When setting up a new portfolio plan over 4 different teams (projects), I've created a new cross-project release and added some epics for each team which are needed for this release. Now, the teams c...
Hi, I was wondering if it was possible to get the stories on the schedule view to be more accurately represented based on the estimate. We currently use an hourly estimate for each story in the sche...
I want to add an additional board/project in Scenario b of my portfolio planning. How can I do that? Reason: I want to separate specific projekt workload from Feature requests and want to show the im...
Hello, We have frontend and backend developers, as well as frontend designers, we create separate tasks for frontend, backend and frontend designers, as they take different amount of time depending ...
One of the teams I am working with has a stable velocity, but will be having a specialist join the team for a few Sprints to address some specific (related) work. The team want to show increased cap...
We are currently using JIRA Portfolio and have dependencies defined in JIRA as Requires and Required by. The configuration of Portfolio has this dependency type specified. Within Portfolio, dependen...
I've got an existing set of ~15 projects which I've reflected in a custom hierarchy (see below). I've ~30 issues at the Initiative level and many more at the Feature level. ...
Hi I'm playing around with Portfolio for Jira for a couple of days and I have a question about showing/tracking progress of epics/stories/sub-tasks. I can see a progress of tasks in Progress column...
I just installed the new trial server version of Jira (7.5) and installed the new version of Portfolio (2.6) and I get this error message. Version:1.0 StartHTML:000000212 EndHTML:000025289 S...
Hi, we need this urgent help, We have customize the workflow in JIRA as per our project requirement and require to pull reports accordingly. So please tell us a way for ...
In the Portfolio plan created, it only shows In Progress and To Do status except the Complete. I want to show Completed tickets in this portfolio as requested by my client. Thanks
I have an epic spanning fixversions with the latest version only containing unestimated work. I have unestimated item scheduling based on target dates. I expected in this scenario for portfolio to ho...
Hey everyone, I can see how to add an absence for a given team member in Jira Portfolio. What I would like to do is export the absences that we have so that we can reconcile this against a HR system...
We have configured the Initiative issue type in JIRA so that we can link Epics together across different projects. In Portfolio, we are able to add child Epics to Initiatives, and in JIRA, I can go t...
Near the end of a sprint, we find that some items didn't finish, and will need to carry over into the next sprint. It would be convenient if we could use Portfolio to incorporate those items into the...