Im having an issue with ranking of issues in portfolio. Expected behavior - Feature can be dragged to top of backlog and all children of the feature (epics and stories) move up in the backlog. After...
We have a 7 hour work day which I can set up successfully when I switch Portfolio to the older interface using Working hours and days. When I switch to the improved interface that configuration setti...
I have been successfully using Portfolio for Jira on a Jira Project for weeks, but now opening Portfolio on the same project results in a completely blank screen. I was updating the values of some st...
we checked below documentation https://confluence.atlassian.com/jiraportfolioserver/configuring-initiatives-and-other-hierarchy-levels-802170489.html we created initiative issue typ...
Currently our Jira test environment is 8.0 version and we have Portfolio plugin for jira 3.0 is installed but I don't see new features in the current test environment. May I know the reason for...
Jira Portfolio 3.0, new experience. My team are starting to use Jira Portfolio 3.0. When we run an auto-schedule, the plan shows some teams are over capacity in certain future sprints....
When I started using Portfolio, the Later release didn't contain any start or end date. But recently I noticed that in some cases (plans) a start and end date is actually assigned to the Later releas...
In Portfolio, we've created a three tier hierarchy: Epic -> Feature -> Story. For some of our Features & Epics, the Scheduled Start & Scheduled End dates are being...
requirements stored for a particular project
I'd like to delete Portfolio since I don't need it.
In my company we're using Jira Software 7.13.0 (server) and I just installed Portfolio (30 days trial license). I'm running into the following problem; I create a shared team and add some u...
I want to use Portfolio for JIRA 3.0 on JIRA cloud. Is it going to come to JIRA cloud anytime soon?
Hello Community! I am looking for sample command to create Initiatives using REST API on Jira with Portfolio. Anyone know how to do it?
I understand how to use Scenarios when you are making changes to a plan that results in the need for Commits. What I want to do is build a Plan in stages. I'm creating Filters and using ...
I am working to implement Portfolio. Version 2.26.0 is currently installed in our test environment by a different admin. I get sent to the Sever documentation when I click on the documentation link. ...
On Portfolio version 3.1 - new experience. I do not understand how the "Target start" and the "Target end" fields are computed by the scheduler. My configuration is: Kanban team with 40h weekly c...
Hi I have connecting projects that do not have parent links - different issue types with normal Jira links. How I can use them to organise the view of portfolio plan to make that one type of the iss...
Earlier post on this went dormant, so I'm looking to reactivate it here. In summary: 1. Created issue types Theme and Initiative in Jira. 2. Created corresponding hierarchy levels in Portfolio. 3....
Hello, I would like to know if it is possible to track data quality on Jira. For example, I would like to see the completion percentage of some fields. I'd be grateful for any help! Have a nice da...
were changes made to the Portfolio icons last week which confused users and we need to find a way to be notified before these happen so that we can prepare our users and avoid problems. Please ...
Does renaming Cross Project Releases in Portfolio cascade to Jira Projects?, if not is there a way to mass update the releases in all Jira Projects?
Hello all, I'm really new to Jira so sorry if my question sounds a little bit dumb. I checked the doc for the Capacity view for Portfolio 3.0 but I'm not able to find the "Capacity view" button...
Hi, I'm trying to configure a Portfolio from our value stream (VS) Kanban, which is on Epic level, but when I list our Epics in Portfolio only 28 Epics show. There should be 60. The VS Portfolio in...
Hi, We have a JIRA server with 100 user license. We now want to test JIRA portfolio with 10 user license. I have bought this 10 user license for exploring before deciding to buy JIRA portfolio...
I have planned future sprints with user stories. In order to prevent them from filling up automatically, I set "Minimum work package size" to 100. If I set the value to 1 or 100, I can see no diffe...