Sarah Moughan November 26, 2025

Hi, today I added about 5 sprints and then on the 6th one, I found that I could no longer edit the End Date. Screenshot below. It seems like Jira is automatically setting the end date 3 weeks after the start date, based on previously created sprints?  What if I need to override the end date for a given sprint, can I still do that?  Thanks. 

end date.png

1 answer

1 accepted

4 votes
Answer accepted
Trudy Claspill
Community Champion
November 26, 2025

Hello @Sarah Moughan 

Welcome to the Atlassian community.

The End Date is grayed out because you have specified a duration for your sprint.

Screenshot 2025-11-26 at 3.36.34 PM.png

Change that to custom and you will then be able to edit the end date.

Screenshot 2025-11-26 at 3.37.42 PM.png

Sarah Moughan November 26, 2025

Trudy, thank you!! I didn't set it to 3 weeks but I am able to change it to custom, just like you said. Thanks so much. 

Trudy Claspill
Community Champion
November 27, 2025

You're welcome!

If my response helped you solve your problem please consider clicking on the Accept Answer button to mark your Question as Solved.