How to roll up Story Point Estimate from subtasks to the Parent (in a Jira Team Managed Project)

Franck Ngnodjom
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
July 1, 2025

Hi Atlassian Community,

I am an administrator of Team Management project and I'm facing an issue on my Jira Cloud version (standard).

I would like to get a sum of my Story Point Estimate from Sub-tasks to parent Story.

I tried to create an automation but I get an error in my last Action because the field "Story Point Estimate" doesn't appear in the drop-down list. Although I can see this field when I create an Issue (US or Task)

So I tried to add that field manually with that code:

{{lookupIssues.Story point estimate.sum}}



That's why there is a warning in the last action. As you can see on the picture below even the steps are in french.

Any insights or suggestions on what might be going wrong or how to fix this would be greatly appreciated.

Thank you!

 

Jira2.PNG

1 answer

0 votes
Geethanjali Katagani
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
July 1, 2025

Hi @Franck Ngnodjom ,

Can you update the automation rule as shown in the screenshot below?
Screenshot 2025-07-01 195329.png
Also, update the "Advanced" action using the JSON format as shown.

Screenshot 2025-07-01 195710.png

Let me know if you need help.

Thanks,
Geethanjali

 