Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

How can I get velocity chart against a sprint? the issues are not estimated in story points but hour

kalyani gupta June 26, 2018

How can I get velocity chart against a sprint? The issues are not estimated in story points but hour.

When we go to velocity chart report under any project, the following message is displayed:

"There are no available sprints for this board." 

1 answer

Tarun Sapra
Community Champion
June 26, 2018

https://jira.atlassian.com/browse/JSWSERVER-9167

Your estimates should be on stories only then it will be taken into account as per the above open issue.

From the comments on above ticket

it affects Velocity chart since we estimate in sub-task level and the original estimate for parent is 0

Suggest an answer

Log in or Sign up to answer
TAGS
AUG Leaders

Atlassian Community Events