I am trying to setup a project in JIRA Kanban template.
In advance roadmaps, I added all the estimates for each tasks and mapped dependencies among the tasks.
When I put in the start date for the first task and click on autoschedule, it doesnt create a right timeline with correct estimates.
Even if the estimate put in is 5 days for a particular task, the timelines populates with different estimates. So the dates I get for project start date and end date are not correct.