The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

portfolio doesn't update Progress

IT Software License
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
April 2, 2015

We have 2 projects with different workflows and progress setting (in Portfolio) by resolved issues. 

In first case Workflow starts from Open and finishes on Closed states and Progress lines work correct (update while creating and closing). 

In second case Workflow starts from New and finishes in Done state. For this case Progress by Resolved doesn't work. (Resolution in second case applied correct, but progress bar shows empty)

How can I fix it? 

3 comments

Comments for this post are closed

Community moderators have prevented the ability to post new comments.

Tanja Nijemcevic
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
August 6, 2015

i have the same issue. Did you figure it out by now?

Chris Mitchell
Contributor
January 7, 2016

Me too. According to Portfolio documentation, if the issue is resolved ( Resolution field is not empty), the progress is 100%.

Tanja Nijemcevic
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
August 6, 2015

I have the same issue. Did you figure it out by now?

Joseph Flynn
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
August 11, 2016

Bump, same problem for me in Aug 2016.  I must be doing something wrong.  Portfolio seems to be excluding completed stories and sub-tasks from the Portfolio dashboard even though I have the setting marked to showing both in progress and done tasks.  Any news?