I'm working in a JIRA cloud instance and testing out Portfolio for JIRA. It says that the estimation fields are required for it to work. I do not seem to have the Original Estimate or Remaining Estimate fields in my JIRA instance. Is there a way to get those back? Or is there a way to map custom estimate fields to Portfolio?
Thanks!
Solved! Go to Solution.
The Time Tracking was active. I granted permissions to application access: Jira software. I went back and tried to add the fields to my issue screens, but it's still not available as a choice.
The field which you have to add is called "Time tracking"
Thank you! This did it! Now I just have to figure out how to make the User Story time tracking will have an effect on the Epic Remaining Time.
Glad to know that it's working, could you please accept/upvote the answer so that other users are helped as well. Thanks.
So is `Remaining Estimate` a field that can no longer be displayed on its own? We don't actually use Jira tickets to log time, so having a `Time Tracking` field on the ticket is extremely confusing.