The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Unable to link boards when creating a new portfolio plan

Oupa Monareng
July 4, 2019

When trying to create a new portfolio plan I can link projects to the plan but when I search for a board that I intend to link in as well I cannot find it on the drop down selection. The board is shared with the project and permissions set on the project allows me to browse the project.

So I'm not sure why I cannot see the board under the board list when trying to link it?

1 comment

Comments for this post are closed

Community moderators have prevented the ability to post new comments.

Earl McCutcheon
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
July 15, 2019

HI Oupa,

When you are selecting the board drop down during the issue sources association, is the board possibly further down on the list that what is rendering?

Can you try using the scroll option to see the boards below the initial list of names that is rendered.

Regards,
Earl