Sub-task Dependencies in Portfolio 2.0

Marie F. Kent
Contributor
June 27, 2016

I found a defect in new version of Portfolio that impacts its use if the teams are using sub-tasks in JIRA

The defect is exposed in two ways:
1) If the sub-tasks have dependencies upon one another, Portfolio will not schedule the story.
2) If the sub-tasks do not have dependencies upon one another, Portfolio will schedule the resources concurrently.
Example:
  • There is a story with three sub-tasks: Design (2 days), Develop (3 days) and Test (4 days).
  • If the sub-tasks are set up so that design blocks development and development blocks testing, Portfolio will not schedule the story and produce errors that there is a violation in dependencies and cyclic dependency detected.
  • If the dependencies are removed, Portfolio will schedule all the resources concurrently. In this example, that would make it appear the designer is working on the story for 9 days and that all resources will start working on the story on the same day.
  • The setting 'Issue assignee import level' in configuration does not address this.
I communicated this to Atlassian and they have logged it as a suggestion.

8 comments

Comment

Log in or Sign up to comment
Eric Babinet
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
August 23, 2016

Do you know what the defect ID is? I believe I am seeing this same issue.

Marie F. Kent
Contributor
August 30, 2016

Hi Eric,

I have not heard back from Atlassian on the stats of the defect and the respondent from Atlassian, rchristian@atlassian.com, did not provide a defect ID. sad

Thanks,

Marie

Michael Seemann
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
October 7, 2016

I encounter the exact same issue here.

in my test setup I have a 

task "testtask" with two subtasks task1 and task2, where task1 blocks task2 (so definitely NOT a cyclic dependency)

 

I also get the "Cyclic dependency detected. "error with a red exclamationmark

Saurabh Agarwal
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
November 10, 2016

Any updates/guidance on this as I am also getting this error and am not able to link 2 Sub-tasks.

mariefkent
November 10, 2016

I have not heard back from Atlassian on this. 

Amir Ghaemian
January 5, 2017

Hitting the same issue, I even tried removing "Block" linktype as a Portfolio dependency linkype but it still complains about cyclic dependency error.

 

Stella Mihovska
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
January 31, 2017

Same issue with me. Any workaround in place?

Marie F. Kent
Contributor
February 8, 2017

I found the record in Atlassian's instance - https://jira.atlassian.com/browse/JPO-1600

Currently, this is listed as a Suggestion and is not assigned.  