We have an epic with many stories, most of them are closed and 1 is open. When we hover over the "Progress (story points)" it shows 0 for completed and 0 for remaining.
As you can see I opened the EPIC and there are many closed stories/tasks. There is also 1 OPEN. Any ideas why this data is not reflected with what is being shown in the epic detailed view ?
Solved! Go to Solution.
Just went to confirm and it is imported as board, and I don't see estimated hours in the stories/tasks.
@Florian Bonniec , so in order for us to see the proper values , we need to have stories, tasks with estimated hours and actual hours data. What about the data source ? Should we be using the filter over the board ?
estimated hours shout be Original Estimate, actual hours data should be the time people log in the ticket it can be found in Time Spent field.
Regards