I have created a virtual user who is not available during some time. When I am planning my user stories on portfolio, i see that portfolio assigns the user to the user story for a given sprint when he is not available. I have tried to check my configuration but haven't found anything. Does anyone would have any idea on this?
Hello @Martin Suntinger,
Thanks for the answering. I already checked the per member view and in fact user stories were assigned to members when they were completely absent from the sprint. After much clicking and switching tabs, I think I figured out what the issue was. In my backlog, I was always fixing a sprint for an epic/user story and not the release. Since I fixed the sprint and the story exceeded the capacity, members who were not available were assigned the user story. When I fixed the release instead and put sprint assignment to automatic, I did not have this issue anymore. And in case work exceeded, the story was automatically assigned to the next sprint.