This question is in reference to Atlassian Documentation: Importing, syncing and updating
I'm trying to use JIRA Portfolio Server to manage many ongoing projects.
During plan creation, I noticed Portfolio only import non-closed issues/epics.
So already completed issue/epic are not applied and calculated in progress report.
I changed workflow scheme to allow editing on closed status to work on them with Portfolio but without importing, it is useless.
Is there any way to import closed issues/epics into Portfolio Scope ?
I figured out myself ![]()
It was due to filter option.
More > Completion Date : default is "Since beginning of Current Sprint" This setting makes all issues out of current sprint not visible.
I changed this setting to Custom Date ( about 6month back ) and now I can see all closed epic/stories as well.
Also, More > Status : should be "Open and completed issues"
I followed your recomendation More> custome completion date , and now it is showing up
This is not working for me. If I change the resolution date filter then it won't show unresolved issues.
Nevermind^ - I figured out that I was just completely in the wrong spot. The only annoying thing now is that the plan has too many issues to expand the stories under epics in the scope view...
These responses only apply to the legacy version of Portfolio The "More > Completion Date : default is "Since beginning of Current Sprint" " is no longer available functionality in the current solution. This causes a great deal of confusion. Please provide an updated link to the current documentation or simply take down this page.
Had the same issues. Several things needs to be imported :
- Make sure to import all closed/released version tagged in closed stories
- More > Completion Date : default is "Since beginning of Current Sprint" to modify with custom date- about a 1 year ago for exemple
- More > Status : should be "Open and completed issues"
Correct me if I'm mistaken but these actions only apply to the legacy UI and not the newer version so in order to access these configurations one must create a roadmap using the "Classic Plan" create option. If the user is not using the dated, legacy, "Classic Plan" then these instructions may not apply. Correct?
I'm not sure to understand the question because portfolio is quite new for me but I didn't had the option of creating a "classic plan" or something else. So these instructions always apply for me because I have only one type of plan.
Not a problem. The "Classic Plan" option is hidden under the 1st step of creating a Live Plan. This and a great deal of Atlassian forum discussions relate to the Classic plan or legacy Portfolio for JIRA solution. See below:
The solution for me to find "done" tickets in my Portfolio plan was the "Resolution" state of the ticket but there is a catch: the new Jira UI doesn't show Resolution, and even after switching to the old version doesn't let you edit the Resolution.
What I end up doing was:
Good luck!