The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Jira Portfolio Capacity calculation

Teija Kurttila
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
May 29, 2018

A question for Jira Portfolio use:

How does Portfolio calculates team capacity for future capacity? Our team sprint capacity is 348  hours per sprint (2 week). Portfolio looks like this for future sprints. Why isn't the sprint (2) full instead it calculates work  also for sprints 3 to 6? We don't have any dependencies in our stories. Shouldn't almost all capacity be on the sprint 2?2018-05-29_12-03-05.jpg 

1 comment

Comments for this post are closed

Community moderators have prevented the ability to post new comments.

Deleted user
May 29, 2018

Hi @Teija Kurttila,

The scheduling behaviour takes into account multiple data points within JIRA. This could be why sprint capacity could be left over.

See a similar question with a response from an Atlassian Team member. 

Hope this helps