Hi!
We created custom sprints for a team. Portfolio automatically assigned stories to sprints. But when the first sprint time was over, Portfolio didn't move stories to the next sprint and didn't signalized that we failed.
Could anybody explain why, please? What is the reason of using Portfolio if it doesn't signalize about such failure and doesn't move stories on and on.
http://prntscr.com/868iaj - printscreen
The same situation is with automatic sprints (sprint1 ... sprintN) http://prntscr.com/868mak
Solved! Go to Solution.
@Martin Suntinger thanks a lot. Really quick and helpful answer. You do a great job with Portfolio! Thanks once again and have a good day!