I don't understand the scheduling logic of portfolio. Low ranked items (n#26 for example_) is scheduled to be developed before the high rank items (n#10). There is no dependencies no earliest dates no other constraints.
I have read all the documentation on Atlassian, they are very high level but I would like to understand how the algorithm makes the choices because many scheduling decisions don't respect our priority of backlog.
Community moderators have prevented the ability to post new comments.
Thank you for your time and support as it's becoming a crucial point for our factory of Dev
Can we please schedule 1h call to show you the plan ?
regards,
Amine
@Earl McCutcheon - Say your velocity is 15. Tickets 1-4 are 3 points each, Ticket 5 is 5 points, and Ticket 6 is 2 points.
The Portfolio algorithm will put Tickets 1-4 in the next sprint because they total 12 points, which the team has capacity to do; however, it won't put Ticket 5 into that same sprint because that would put it at 17 (above capacity). Instead it will put Ticket 6 in and save Ticket 5 for the sprint after that.
Is there a way to disable that behavior? Meaning, is there a way to enforce Ticket 5 to be put into the next sprint along with Tickets 1-4, perhaps to split the ticket across sprints (i.e. 3 points of Ticket 5 in this sprint, 2 points of Ticket 5 in the next)? Alternatively, can Ticket 5 be assigned to this sprint and be flagged to indicate a risk of completing the work in the sprint given the team has a lower velocity than the total amount of story points per that sprint?