The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

JIRA Portfolio Hours not adding up

kdolhay
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
March 5, 2018

When evaluating the summary of hours from JIRA Portfolio the hours remaining add up to a considerable higher number than the numbers that show when I manually go into each story and add up the remaining hours.  I've cleared my Cache as I believe Atlassian has said this sometimes can be an issue but if others have experienced this please advise.

 

1 comment

Comments for this post are closed

Community moderators have prevented the ability to post new comments.

Gabriel Senna
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
April 6, 2018

Hi Kevin,

I checked internally and I could find that you raised a ticket for the support and it was answered there.

I'm posting the answer here, so others can use it.

Using example with issue

If you select the issue FPDSC-1047 estimation, you will see 81+90.

81 is the sum of all sub-tasks, 90 is the number of hours associated to the issue FPDSC-1047.

If you open the issue FPDSC-1047, you will see that this issue have no estimation in hours, but 15 story points.

Checking your plan issue source, 1 Story point = 6 hours, so the issue FPDSC-1047 have 90 hours estimated.