The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Issues not assigned to sprint

Kevin Bruce
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
July 16, 2023

I am using the sprint capity management view and I am getting the warning on some teams "X issues are not assigned to sprint" is there anyway that I can view what these issues are? IMG_20230716_193732_edit_121071834161733.jpg

1 comment

Comments for this post are closed

Community moderators have prevented the ability to post new comments.

Ojase Emmanuval
Community Champion
July 16, 2023

@Kevin Bruce Welcome to the Atlassian community !!

The advanced roadmap make use of start date and due date fields to determine issues assignment to sprint. You can run a JQL query to fetch all issues which are scheduled between your sprint start date and end date and not assigned to the sprint. The JQL query will look something similar to the following.

start date= "insert sprint start date here" and due date="insert sprint end date here" and sprint != "inset your current sprint id" and team ="X"

Thanks,

Ojase