Are dependencies at the sub-task level supported in JIRA Portfolio?
When I establish dependencies between sub-tasks in JIRA Portfolio and click the button to recalculate the schedule, the scheduler returns errors. The error at the sub-task level is:
The errors at the main task level are:
On a related note, the scheduler seems like it can get itself into a state that is almost unrecoverable. When trying to work through the above issue, I added and deleted a lot of dependencies trying to find something that worked. Sometimes the scheduler would still return errors even when I'd deleted all dependencies. Anyone else having that issue?
Solved! Go to Solution.
What is the reason for not allowing dependencies within a task? In my scenario working with a Marketing group, the task is to produce a piece of copy. To accomplish this, there is a sub-task to write the copy and a sub-task for the requester to review the copy. The review is dependent on the copy being written.
Peter,
No, sub-tasks cannot have dependencies in Portfolio. Here is the write-up from last year. Sub-task Dependencies in Portfolio 2.0
Also, if you remove the dependencies, Portfolio will schedule all the resources concurrently.
In short, you cannot use sub-tasks in Portfolio plans.
Atlassian has this as a suggestion, I advise people to vote on this and add a comment that it is a defect. https://jira.atlassian.com/browse/JPO-1600
Hope this helps!