The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

In portfolio I have a release showing as "overbooked" while i still have capacity available

Mathieu Lapre
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
January 23, 2018

I am using portfolio with a kanban team.  The team contains 9 members with 40 hrs per week capacity.  I have 6 stories.  5 of them are assigned to 5 members of the team (one per person).  Portfolio therefore predicts each story will take a month to perform based on one assignee doing a story.  The capacity shows that for each week, I have 4 member of free capacity left.  My 6th story is not assigned to anyone.  This 6th story is assigned to a different release but this release as the same start date as the other release to which the other 5 stories are tagged.

In the portfolio setting, I have set the option that up to 12 people can work on a single story.  Therefore, I would expect that this 6th story that is unassigned would use up the capacity available each week and start in parallel with the 5 others.  Instead, portfolio forces it to start only once the other 5 assigned stories are done.  When I look at the capacity, it is ridiculous because I see that my team is occupied at 50% during the time the team works on the 5 assigned task.  HOw can I force parallelization of the tasks.

 

thanks

Mathieu

1 comment

Comments for this post are closed

Community moderators have prevented the ability to post new comments.

Cindy
September 12, 2018

Do you have any dependencies?