We have 3+ levels in Jira Portfolio:
We'd like to remove Business Epic from this hierarchy.
If we do that, would Epics that had Business Epic as Parent Link automatically be attached to correct Scopes?
Or should we first do some manual changes before removing the level?
Solved! Go to Solution.
Thank you for the help! Although as we have Jira in Cloud and not on server some of the JQLs don't seem to run, but we'll manage anyway.
Just to doublecheck - will we just lose Parent Link from Epics to BE, or will BE issues be removed entirely?
Hi Joanna,
When you remove the BE "Business Epic" initiative hierarchy, the issues will still be there but as a standard issue type in the hierarchy now, (so considered at the story level below the epic level) just no longer considered an initiative. Unless you want to get rid of them because you're no longer using the type, and manually remove the issues, which you could do by removing the issue type from the projects issue type scheme and converting the existing BE issue to another type.