I'm generating a plan in protfolio for Jira Cloud. I set the sprint to "calculate", for each story, for Portfolio to calculate it dynamicaly. I am happy with the result but when i want to commit these changes and assign the stories to sprints,
The only way to assign stories to sprint is to set the sprint manually in portfolio.
I made a test using the sample data from a new project.
Thanks
Solved! Go to Solution.
I think this must be a browser caching issue because the next day, the button where there.
Hi, I found this problem and it was due to me setting the filter view options to Epic and not Story!