Say you have a team that can accomplish 10 points per sprint and there are 3 people on the team? Does it do a split that each team member can do 3.33 points? Or what is the logic on this?
Thanks in advance!
Solved! Go to Solution.
@Shannon S - Thanks, Lets say resource A is at 30 hours and Resource B is at 15 hours, how will it change the amount? Will it reduce the velocity half for that resource in total?
Think of it this way.
Say the team has a velocity of 10 story points. You have two team members, and they work 15 hours and 30 hours, respectively, so a total of 45 hours for the team.
We need to work 10 story points in 45 hours, so they will be divided accordingly.
Thus, a 30 hour work week would do 6.66 story points, and 15 would be 3.33.
Essentially, if team member A works twice as more hours then B, then A will do twice as more story points as B.
Hope that's clear! Do let me know if you have any questions.
Regards,
Shannon
You're welcome, David! Happy I was able to help.
Regards,
Shannon