The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

How do you deal with issues that take more time than manpower-time?

Christoph Baumeister
Contributor
February 21, 2018

My question is how to include issues into roadmap planing that take 10 days, but only require 5 days of real work because there is some external dependency. As a consequence the engineer only needs to be blocked by 5 days, but the whole issue needs to be planned with 10 days. Any suggestions?

1 comment

Comments for this post are closed

Community moderators have prevented the ability to post new comments.

Steve Thornhill
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
February 21, 2018

Have you considered using sub-tasks within the issue.

  • Sub-task one for 5 days as external work.
  • Sub-task two for the engineer, but blocked by sub-task one.
Christoph Baumeister
Contributor
February 21, 2018

@Steve Thornhill Thanks! And then assigning the external sub-task to a fictive "external" team?

Steve Thornhill
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
February 21, 2018

Yep, the sub-task doesn't need to be assigned, but if you are likely to use it for reporting then it would make sense to have an 'external' user/team rather than just being unassigned.