In Portfolio, we've created a three tier hierarchy: Epic -> Feature -> Story. For some of our Features & Epics, the Scheduled Start & Scheduled End dates are being accurately calculated based on the sprints that the stories are in (example1 screenshot).
Other Features & Epics seem to be calculating their Scheduled Start dates incorrectly. The stories have accurate Scheduled Start dates, but the Feature & Epic do not (example2 screenshot).
This matters because Epics with incorrect Scheduled Start dates make the Schedule view inaccurately look like we're working on those Epics when we're really not.
Does anyone know why this might be and how I can correct it?