The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Does anyone know how to get capacity to show in the 'projected sprint' area on an advanced Roadmap

Jason Lefler
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
May 21, 2020

I have been trying to capacity plan in the new Advanced Roadmaps that replaced Portfolio for Jira and so far I have only been able to get the points vs velocity to show in a 'current sprint' in the roadmap but not in the 'projected sprint'. Any thoughts as to why that might be happening or what I can do different?

Thanks.

1 comment

Comments for this post are closed

Community moderators have prevented the ability to post new comments.

Roi Fine
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
May 24, 2020

Hi Jason,

The estimates allocation vs velocity info is only available for active or future sprints. You can create future sprints in your Jira board and estimate/velocity information would become available in the plan.

Nonetheless, that is a good feature suggestion. I would encourage you to create a suggestion ticket here so other users could comment and vote for it. 

I hope that helps, happy to hear your thoughts.

Cheers,

Roi