Hi All,
I'm hoping someone can help advise on possible approaches to this problem I am facing. I have a project that spans multiple business units from marketing to legal and technology to compliance. My technology team would like to use story points for estimation however my compliance and legal team work on tasks that are extremely sequential in nature hence they want to use man days. For example: .... we make an application with with a government then they respond with x days then we do the next step.... so it kind of goes against the entire agile mindset. Am I trying to achieve the impossible here by combining the two different approaches?
Any ideas on how I can accommodate both approaches but integrate into a single portfolio/plan?
cheers
Andrew