Im just getting set up with Jira and Portfolio after moving away from Asana. We have been used to setting due dates for when work should be completed, and while I know that due dates can be set in an issue view, how can I go about setting up due dates for issues based on the schedule created in Portfolio. Ideally, I would get a schedule for a based on capacity, make adjustments for priorities, and then when the updates are committed, the due dates would be set for items inside of the Jira issues.
Hi @George Birnbaum,
I would suggest using the Target start and Target end date fields provided by Portfolio for this. (Docs for Server and Cloud).
Cheers,
Thomas