Im just getting set up with Jira and Portfolio after moving away from Asana. We have been used to setting due dates for when work should be completed, and while I know that due dates can be set in an issue view, how can I go about setting up due dates for issues based on the schedule created in Portfolio. Ideally, I would get a schedule for a based on capacity, make adjustments for priorities, and then when the updates are committed, the due dates would be set for items inside of the Jira issues.
Community moderators have prevented the ability to post new comments.
Hi @George Birnbaum,
I would suggest using the Target start and Target end date fields provided by Portfolio for this. (Docs for Server and Cloud).
Cheers,
Thomas