Hi,
I use Portfolio 2.17. We have calculated fix versions and calculated sprints on most of our stories and epics.
We want to propagate this back to jira. I followed the "Assigning issues to sprints": https://confluence.atlassian.com/jiraportfoliocloud/assigning-issues-to-sprints-828785264.html
From Scope view: I see I can manually re-select the calculated sprint value. This is a high effort for each and every story or epic. Seems not to be practical.
From Timeline view:
The sprint is in jira, issue as well. Each story is only in one sprint, issues are not already assigned to sprint, calculate is done etc.
If I click in the timeline to the sprint, I can see the statistic free capacity, planned capacity, capacity utilization, but I can't see the assign 2 calculated issues.