I am new to Advanced Road Map. Is there a way that when I update my "Estimates (d)" column that it automatically adjusts my due date (planned finish date)? This would be much like using the duration in Microsoft Project. If I move my duration from 2 to 5 days, it will automatically push my planned finish date out by 3 days and adjust any dependency taks dates based on this adjustment. This is very crucial in Project Managment especailly if you are managing multiple projects because having to manually adjusts the dates will be a nightmare and there is room for user error. If there is, how do I do this? Are there any live webinars for Advanced Roadmaps where I can actually ask the experts some of these questions or even an expirt at Atlassian that I can talk with directly?
Thank you,
Jeanne