  • If estimate of Portfolio Plan has mapping with remaining estimate of linked issue, why do changing estimate value on plan updates remaining as well as original estimates of linked issue with estimates from Plan.

If estimate of Portfolio Plan has mapping with remaining estimate of linked issue, why do changing estimate value on plan updates remaining as well as original estimates of linked issue with estimates from Plan.

.

1 answer

0 vote

The assumption is: As long as no plan updates have been made and there is no value for "Originally planned" set in JIRA Portfolio (you can see this column only when using the "Show completed issues" toggle), then we have a case of doing the initial planning, in which we're rather working with the initial (original) estimates, and what is remaining to be scheduled will be the same value, thus both of them are set to the same value on sync.

Once you've done a plan update, and the previous estimates are stored as "Originally planned", the sync with update only the remaining estimate field on the JIRA issues, and the value in the "orignally planned" column is synced to the original estimate. 

In short: We assume during initial planning, we're rather estimating the original values, and original=remaining, later when updating, only the remaining is synced. 

Suggest an answer

Log in or Join to answer
Community showcase
Josh Frank
Posted Dec 01, 2017 in Portfolio for Jira

Portfolio for Jira: Share your tips!

The Portfolio for Jira team wants to hear from you. Share your top tips for building a great Portfolio for Jira plan for a chance to win some Atlassian swag.  Do you structure your teams i...

567 views 6 8
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot