The original Estimate is what you plan it for. The remaining estimate is based against the the timed logged against the issue. So, if you spent 4 hours of the original estimate of 10 hours, then the remaining estimate is 6 hours.
Hope this helps.
-Ben
Thanks @Benjamin
The issue here is when we modified "Original Estimate" a second time.
For example: we estimate the task with 10 hours, then "Remaining Estimate" is 10 hours (since we haven't log any time). After than, we change "Original Estimate" to 20 hours and "Remaining Estimate" is still 10 hours.
Do you know if this is the normal behaviour or there is a way to refresh the field "Remaining Estimate" reflecting the new "Remaining Estimate"?
Thanks!