Is it possible to see combined hours for all tasks for user stories for each individual for the spr

srinath
Contributor
August 24, 2018

Is it possible to see combined hours for all tasks for user stories  for each individual for a particular  sprint? Please let me know available options.

1 answer

0 votes
Magic Mike
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 26, 2018

Do you mean in term of estimation or logged work?

srinath
Contributor
August 26, 2018

It's for the estimation and also it would be really if we have both.

Magic Mike
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 27, 2018

You could have Story Points set for your Scrum Board (you can only choose one estimation type per Board). So you could check the Agile reports. Regarding estimation in time you have the project reports (time estimate) you can filter by release. In both cases if you have more than user stories you might not be able to filter by US only.

srinath
Contributor
August 29, 2018

Donikian- I did't get your solution. Could you please explain with an example.