I'm having issues with checklists being completed but not having the the Checklist Completed field = Completed.  I just figured out how to add a new separate checklist but having a hard time completing the checklist, when I choose completed and says 3/3 for progress, Checklist Completed still equals Not Completed.   

Are there any other checklist addons that will work with automation for jira? 

Thanks!

 

1 answer

1 accepted

0 votes
Answer accepted

Looks like Checklist Completed actually needs to equal "All Completed", not "Completed" as was stated in the documentation. 

Hello David,

Indeed, the correct value for Checklist Completed field, when all items are checked is "All Completed". 

It changed when we introduced mandator-optional items feature a few months ago.

We will change the docs.

Thanks!
Jack 