Capacity Tracker - How to use when planning a sprint that has not started yet?

I have a active sprint (sprint 1) and I am now planning sprint2, which of course did not start yet.

Since Sprint2 did not start, it does not have dates.

In Capacity Tracker, this means that I can't see team and individual load.

Recommendations?

Thanks!

1 answer

Hi Ofer,

The Tracker is now upgraded with full planning capabilities.

When you select a future sprint in the sprint selection dropdown you will now find two fields in the configuration section.

Fill your start date and end date and your sprint will now have planning capabilities.

We hope this will help you in your use cases.

 

Regards,

The Inprowiser Team.

i'm using the latest version of capacity tracker - how ever i have the same issue with planning future sprint - and i cannot find the two fields of the dates setting 

is it possible to have some screen shot of this?

Hi,

this was changed after Jira introduced their own future sprint start and end date. You can now configure this on the sprint itself and the tracker will pull the dates from Jira.

Let us know if you have any more questions.

 

Regards