You're on your way to the next level! Join the Kudos program to earn points and save your progress.
Level 1: Seed
25 / 150 points
Next: Root
1 badge earned
Challenges come and go, but your rewards stay with you. Do more to earn more!
What goes around comes around! Share the love by gifting kudos to your peers.
Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!
Join now to unlock these features and more
The Atlassian Community can help you and your team get more value out of Atlassian products and practices.
helo everyone, i have problem with jira report. i estimate for task in sprint. but when i running sprint, i can't see a burndown report. please help me urgent !
Welcome to the Atlassian Community!
Assuming it is a Company-managed scrum or kanban
1> we using subtask, it not working for burndown and burnup chart, right?
2> we will hide task when done in last column, it mean all task in close sprint will not show in active sprint. so velocity can't show it, right?
1. Burndown is a function of sprints. Sub tasks (in Jira) are part of a story, not sprint items. So sprint estimation on sub tasks is nonsense. Do not do it (other estimation is fine, just not sprint/scrum)
2. If you hide it, then by definition, you cannot report on it.
Help you with what? We've already explained what you're doing that needs to change.