Hello,
I have a few stories in 1 sprint (2 weeks). I estimate story point for each story.
I will have a few subtasks under a story.
Q1. My question is, as best practice, do I create these subtasks and provide time estimates before the start of a sprint?
Q2. Do I also need to provide Estimate Time at story level other than story point?
Q3. How about at subtask level, do I provide time estimates to see a meaningful burndown chart?
Q2. Does one normally also create subtasks and time estimates after the start of a sprint? Am I right to say this will impact burndown chart to go up?
Thank you.
Thanks @Ollie Guan
Re 2, if i use story point, do i provide time estimate for my subtasks?
Or if I use Time Estimate, so I just need to provide these Time Estimate at both story and subtask level? And I can ignore story point at story level?
Yes, I think they can be both, or just one.
Recommended Learning For You
Level up your skills with Atlassian learning
Jira Align Program Essentials
Learn how to use Jira Align at the program level and how to plan for and manage your Program Increment (PI).
Managing Agile Boards and Reports
Learn how to pick the right board type for your team and customize it to fit your specific requirements.
Atlassian Certified Associate
Jira Software Board Configuration
Earn an associate-level credential from Atlassian that shows you can effectively configure Jira Software boards.