Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Come for the products,
stay for the community

The Atlassian Community can help you and your team get more value out of Atlassian products and practices.

Atlassian Community about banner
4,556,047
Community Members
 
Community Events
184
Community Groups

Sprint Volatility Reporting

We have an organization with about 800 JIRA projects.  One of the new Agile metrics being discussed is 'Sprint Volatility' or % change in scope during the sprint: [(# story points dropped + # story points added) / story points committed*]  

Note: In this instance, 'story points committed' is NOT the same as the story points included at the start of the sprint, but rather the end result of story points committed, then removed and any added.  

Do other organizations utilize this metric to manage their sprints and teams?

How is it actioned?   

Will JIRA need to produce this value and if so, where would you want it to be included... within the Velocity Chart? 

1 comment

same question that I have, hoping ATLASSIAN will find ways to plot on this in JIRA environment so that we can easily use it.