Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Move Epics out of Sprint if Stories are in Backlog

I have a long-duration Epic (2 years), that has a bunch of Stories associated with it. Most of the Stories have been completed in previous Sprints. We are planning the remaining Story of the Epic about three to five Sprints from now. The Epics, however, continue to show up in each Sprint even if we are not working on it. So the question:

Can we hide the Epic from the Sprint without removing the related Story? Is there another option?

Thanks,

Randall

1 comment

YES, it is possible to hide epics from sprints . But sorry I have not had a chance to explore how to enable it on Jira . My admin did it for me. 