Does anyone use the Kanban board with sprint time boxes?

If so, what report/metrics do you use to view progress?

- Would it still be the control chart against real time it took to complete issues?

In general, how do you show progress for Kanban if there's no "committed amount of work in a time period"?

We'd like to use sprints to be able to plan for what will be done in this 2 weeks, what will be done in the next 2 weeks, and so on.

1 comment

Warren Levy Community Champion Nov 06, 2017

We don't work like that, so can't specifically comment, but a very good report to use for Kanban is the Cumulative Flow Diagram (CFD). The CFD can still be used with a Scrumban approach (and even pure Scrum), so take a look at the one in Jira and do a search of what info the CFD can give you.

Comment

Log in or Join to comment
Community showcase
Sarah Schuster
Posted Jan 29, 2018 in Jira

What are common themes you've seen across successful & failed Jira Software implementations?

Hey everyone! My name is Sarah Schuster, and I'm a Customer Success Manager in Atlassian specializing in Jira Software Cloud. Over the next few weeks I will be posting discussion topics (8 total) to ...

2,760 views 11 18
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot