[Big Picture] [Resource Management] Fill in original estimate and logwork to use?

Nguyen Ngoc Tram _FHM_INS_ November 21, 2021

Hi everyone,

I was a bit confused when I first used the Resource Management feature on Big Picture.
To calculate capacity, I need to fill in an original estimate and my members must logwork?
Do I need to fill (start date - end date) or (create date-due date)?

 

Thanks,

Nguyen

1 comment

Comment

Log in or Sign up to comment
Anna-BigPicture
Marketplace Partner
Marketplace Partners provide apps and integrations available on the Atlassian Marketplace that extend the power of Atlassian products.
November 25, 2021

Hi @Nguyen Ngoc Tram _FHM_INS_

Do you refer to Team or Individual Resource Capacity?
 
The capacity of your resources is calculated based on Workload Plans and non-working days resulting from Holiday Plans and individual Absence Plans.
 
However, the formula of Team capacity is just a sum of the individual capacities of team members.
 
Here you will find a more detailed explanation: Capacity calculation.
 
Then if you have further questions or doubts, just tag me in this thread. 