[Big Picture] [Resource Management] Fill in original estimate and logwork to use?

Hi everyone,

I was a bit confused when I first used the Resource Management feature on Big Picture.
To calculate capacity, I need to fill in an original estimate and my members must logwork?
Do I need to fill (start date - end date) or (create date-due date)?

 

Thanks,

Nguyen

1 comment

Anna-BigPicture Marketplace Partner Nov 25, 2021

Hi @Nguyen Ngoc Tram _FHM_INS_

Do you refer to Team or Individual Resource Capacity?
 
The capacity of your resources is calculated based on Workload Plans and non-working days resulting from Holiday Plans and individual Absence Plans.
 
However, the formula of Team capacity is just a sum of the individual capacities of team members.
 
Here you will find a more detailed explanation: Capacity calculation.
 
Then if you have further questions or doubts, just tag me in this thread. 

Comment

Log in or Sign up to comment
TAGS

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you