Jira lets you reopen sprints that have been previously closed. This is a handy feature when:
Moreover, sprints that are mistakenly closed or closed too early will affect your team's velocity, as the data in these sprints will still be included in your board. Your Velocity Chart will then be reflecting inaccurate data.
To reopen a sprint, you must be logged in as a user with the Jira administrator permissions or a user with the manage sprints permission. For details, see Permissions overview.
Navigate to your desired board.
Select Reports, and then select Sprint Report.
Select the relevant sprint from the sprint drop-down
Select Reopen Sprint. The Reopen Sprint dialog will be displayed, showing you the outcome you can expect when the sprint is reopened.
Select Reopen.
Note the following details that take place when a sprint is completed then reopened: