Automatically calculate time when item is transacted

Gustavo November 20, 2023

I wanted to know how this can be done, I have a problem, when I use time control, I am forced to enter the value, so I wanted to know if with an intelligent value it is possible to do this automatic calculation of the item when it moves to another stage .

1 answer

0 votes
Muhammad Moazzam Hassan
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
November 20, 2023

There is one method from which you can achieve this but it requires an automation rule.

1: Create two Fields - Date and Time: e.g A and B.

When the issue transitions to status In Progress field A is set to {{now}} and when it transitions from In Progress to Done then field B is set to {{now}} and calculates the time difference to another field, and clears the  A and B fields.