Sprint raport status of tasks

bartlomiej_jochym February 28, 2024

Hi,

Is it possible to separate completed subtasks from others?

When I want to create a sprint report of 1 story with 3 subtasks (2 completed and 1 to  do), the report treats our story as "Issue Incomplete" even though two subtasks have been completed.

 

Story

Screenshot 2024-02-28 at 23.20.05.png

Report

 

Screenshot 2024-02-28 at 23.18.23.png

 

1 answer

0 votes
Danut M _StonikByte_
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 28, 2024

Hi @bartlomiej_jochym

The report is correct, because the story is incomplete, due to the fact that not all the sub-tasks were completed. If you want the issue to appear as completed, try to manually change its status to Done. 